Project docket
Docket No:
PUC Docket # PL5/PPL-05-2003
Project name:
MinnCan Project--Minnesota Pipe Line Company
Applicant:
Minnesota Pipe Line Company
Description:
Proposed 295-mile between Clearbrook, MN in Clearwater County and the Flint Hills Resources refinery in Rosemont, MN in Dakota County
Subjects:
Environmental policy; Pipelines
Location:
Minnesota; Twin Cities Metropolitan Area; Clearwater County; Hubbard County; Wadena County; Todd County; Morrison County; Stearns County; Meeker County; Wright County; McLeod County; Carver County; Sibley County; Scott County; Dakota County
Docket created:
January 08, 2006
Status:
02-16-2006 Application accepted |
03-13-2006 Public meeting |
07-19-2006 Routes accepted for consideration |
08-24-2006 Public hearing |
04-13-2007 Permit issued |
Project built |
Docket closed |
Mailing list:
• Register (if you have never established an account) Or
• Sign on (if you already have established an account for other mailing lists)
This page provides documents relevant to the Pipeline Route Permit Application for the MinnCan Project that was submitted by Minnesota Pipeline Company (MPL) on January 5, 2006.
In addition to the Route Permit Application, MPL filed an application for a Certificate of Need for the MinnCan Project on January 3, 2006, the matter was assigned to Docket No. PL-5/CN-06-2.
On April 13, 2007, the Minnesota Public Utilities Commission (PUC) issued its Order Granting a Certificate of Need. The Order can be accessed through the following link:
Order Granting a Certificate of Need
Additional documents relevant to the Certificate of Need and Route Permit Proceedings can be view through the eDockets search page by entering docket number 06-2 for the Certificate of Need Proceeding and docket number 05-2003 for the Route Permit Proceeding.
eDockets Search Page
|
| Date | Project name | Description |
| April 13, 2007 |
PUC Order Granting a Route Permit for the MinnCan Pipeline Project
| document details
|
Minnesota Public Utilities Commission Order Granting Route Permit for the MinnCan Pipeline Project |
| February 02, 2007 |
MinnCan Pipeline Route Maps as of January 5, 2007 |
Pipeline Route Maps in the Matter of the MinnCan Crude Oil Pipeline Indicating the Proposed Route as of January 5, 2007 |
| February 02, 2007 |
Comments and Recommendations to the Minnesota Public Utilities Commission in the Matter of the MinnCan Project |
Comments & Recommendations of the Department of Commerce Energy Facility Permitting Staff in the Matter of the MinnCan Crude Oil Pipeline Project |
| February 09, 2007 |
Supplement to MinnCan Comments and Recommendations
| document details
|
Supplement to Comments and Recommendations of the Department of Commerce Energy Facility Permitting Staff in the Matter of the MinnCan Crude Oil Pipeline Project |
| April 13, 2007 |
Notice of PUC Order Granting Approvals for the MinnCan Pipeline Project
| document details
|
PLEASE TAKE NOTICE that on April 13, 2007 the Minnesota Public Utilities Commission issued two separate Orders granting a Certificate of Need and a Pipeline Routing Permit for the MinnCan Pipeline Project |
| November 17, 2006 |
Administrative Law Judge Heydinger’s Report providing Findings of Fact, Conclusions and Recommendations in the matter of the MinnCan Pipeline Project
| document details
|
The Administrative Law Judge’s Findings of Fact, Conclusions and Recommendation in the Matter of the Application of Minnesota Pipeline Company for a Certificate of Need for a Crude Oil Pipeline and in the Matter of the Application of Minnesota Pipeline Company for a Routing Permit for a Crude Oil Pipeline |
| February 17, 2006 |
Pipeline Routing Permit Application-MinnCan Project PUC Docket # PL-PL-05-2003
| document details
|
Minnesota Pipe Line Company MinnCan Project |
| February 17, 2006 |
Environmental Assessment Supplement to the Pipeline Routing Permit Application
| document details
|
MinnCan Project--Minnesota Pipe Line Company |
| February 17, 2006 |
PIPELINE ROUTING PERMIT APPLICATION-FIGURES-- MINNCAN PROJECT PUC DOCKET # PL5/PPL-05-2003
| document details
|
MinnCan Project--Minnesota Pipe Line Company |
|
| Date | Project name | Description |
| April 13, 2007 |
PUC Order Granting a Route Permit for the MinnCan Pipeline Project
| document details
|
Minnesota Public Utilities Commission Order Granting Route Permit for the MinnCan Pipeline Project |
| April 13, 2007 |
Notice of PUC Order Granting Approvals for the MinnCan Pipeline Project
| document details
|
PLEASE TAKE NOTICE that on April 13, 2007 the Minnesota Public Utilities Commission issued two separate Orders granting a Certificate of Need and a Pipeline Routing Permit for the MinnCan Pipeline Project |
| February 09, 2007 |
Supplement to MinnCan Comments and Recommendations
| document details
|
Supplement to Comments and Recommendations of the Department of Commerce Energy Facility Permitting Staff in the Matter of the MinnCan Crude Oil Pipeline Project |
| February 02, 2007 |
MinnCan Pipeline Route Maps as of January 5, 2007 |
Pipeline Route Maps in the Matter of the MinnCan Crude Oil Pipeline Indicating the Proposed Route as of January 5, 2007 |
| February 02, 2007 |
Comments and Recommendations to the Minnesota Public Utilities Commission in the Matter of the MinnCan Project |
Comments & Recommendations of the Department of Commerce Energy Facility Permitting Staff in the Matter of the MinnCan Crude Oil Pipeline Project |
| November 17, 2006 |
Administrative Law Judge Heydinger’s Report providing Findings of Fact, Conclusions and Recommendations in the matter of the MinnCan Pipeline Project
| document details
|
The Administrative Law Judge’s Findings of Fact, Conclusions and Recommendation in the Matter of the Application of Minnesota Pipeline Company for a Certificate of Need for a Crude Oil Pipeline and in the Matter of the Application of Minnesota Pipeline Company for a Routing Permit for a Crude Oil Pipeline |
| August 02, 2006 |
Notice of Public Meeting and Public Hearings on the MinnCan Pipeline Project
| document details
|
Notice of Public Meetings and Public Hearings regarding the applications by Minnesota Pipeline Company for a Certificate of Need and a Pipeline Routing Permit for the 295 mile MinnCan crude oil pipeline project |
| June 22, 2006 |
Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipline project
| document details
|
Comments and Recommendations of the Commerce Department Staff concerning what additional pipeline alignments, route segments and route alternatives should be accepted by the PUC for consideration at a contested hearing. Attachments to the Comments and Recommendations are listed separately |
| June 22, 2006 |
Attachment D of the Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipeline project
| document details
|
Attachment D -- Relevant correspondence concerning additional pipeline alignments, route segments and route alternatives. |
| June 22, 2006 |
Attachment C of Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipline project
| document details
|
Attachment C -- Route/Route Segment Proposals Outside of Proposed Route |
| June 22, 2006 |
Attachment B to Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipline project
| document details
|
Attachment B -- Alignment Modifications within the MPL Proposed Route |
| June 22, 2006 |
Attachment A to Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipline project
| document details
|
Attachment A -- Pipeline routing process schematic and other background materials |
| March 22, 2006 |
Guidance for Route Proposals
| document details
|
This gudiance document provides a summary of what interested parties must do to submit an alternative route or route segment for consideration by the Public Utilities Commission |
| March 03, 2006 |
MinnCan Permit Process Schematic
| document details
|
Permit process flowchart with dates specific to the MinnCan Project |
| February 21, 2006 |
Notice of Pipeline Routing Permit Application Acceptance and Public Information Meetings on the MinnCan Pipeline Project
| document details
|
Information Meetings on the MinnCan Pipeline Project |
| February 17, 2006 |
Pipeline Routing Permit Application-MinnCan Project PUC Docket # PL-PL-05-2003
| document details
|
Minnesota Pipe Line Company MinnCan Project |
| February 17, 2006 |
PIPELINE ROUTING PERMIT APPLICATION-FIGURES-- MINNCAN PROJECT PUC DOCKET # PL5/PPL-05-2003
| document details
|
MinnCan Project--Minnesota Pipe Line Company |
| February 17, 2006 |
Environmental Assessment Supplement to the Pipeline Routing Permit Application
| document details
|
MinnCan Project--Minnesota Pipe Line Company |
| January 26, 2006 |
Briefing Paper re Pipeline Routing Permit Application for the MinnCan Project
| document details
|
Staff Briefing Paper Regarding Acceptance of Pipeline Routing Permit Application |
| January 26, 2006 |
MinnCan General Project Location Map
| document details
|
MinnCan General Project Location Map |
|