skip to content

Project docket

Docket No: PUC Docket # PL5/PPL-05-2003
Project name: MinnCan Project--Minnesota Pipe Line Company
Applicant: Minnesota Pipe Line Company
Description: Proposed 295-mile between Clearbrook, MN in Clearwater County and the Flint Hills Resources refinery in Rosemont, MN in Dakota County
Subjects: Environmental policy; Pipelines
Location: Minnesota; Twin Cities Metropolitan Area; Clearwater County; Hubbard County; Wadena County; Todd County; Morrison County; Stearns County; Meeker County; Wright County; McLeod County; Carver County; Sibley County; Scott County; Dakota County
Docket created: January 08, 2006
Contacts: Larry Hartman, 651-296-5089, State Permit Manager.
Status:
 
02-16-2006
Application accepted
 
03-13-2006
Public meeting
 
07-19-2006
Routes accepted for consideration
 
08-24-2006
Public hearing
 
04-13-2007
Permit issued
 
Project built
 
Docket closed
Mailing list: • Register (if you have never established an account) Or
• Sign on (if you already have established an account for other mailing lists)

This page provides documents relevant to the Pipeline Route Permit Application for the MinnCan Project that was submitted by Minnesota Pipeline Company (MPL) on January 5, 2006.

In addition to the Route Permit Application, MPL filed an application for a Certificate of Need for the MinnCan Project on January 3, 2006, the matter was assigned to Docket No. PL-5/CN-06-2.

On April 13, 2007, the Minnesota Public Utilities Commission (PUC) issued its Order Granting a Certificate of Need.  The Order can be accessed through the following link:

Order Granting a Certificate of Need

Additional documents relevant to the Certificate of Need and Route Permit Proceedings can be view through the eDockets search page by entering docket number 06-2 for the Certificate of Need Proceeding and docket number 05-2003 for the Route Permit Proceeding.
 

eDockets Search Page

Primary documents
DateProject nameDescription
April 13, 2007 PUC Order Granting a Route Permit for the MinnCan Pipeline Project | document details Minnesota Public Utilities Commission Order Granting Route Permit for the MinnCan Pipeline Project
February 02, 2007 MinnCan Pipeline Route Maps as of January 5, 2007 Pipeline Route Maps in the Matter of the MinnCan Crude Oil Pipeline Indicating the Proposed Route as of January 5, 2007
February 02, 2007 Comments and Recommendations to the Minnesota Public Utilities Commission in the Matter of the MinnCan Project Comments & Recommendations of the Department of Commerce Energy Facility Permitting Staff in the Matter of the MinnCan Crude Oil Pipeline Project
February 09, 2007 Supplement to MinnCan Comments and Recommendations | document details Supplement to Comments and Recommendations of the Department of Commerce Energy Facility Permitting Staff in the Matter of the MinnCan Crude Oil Pipeline Project
April 13, 2007 Notice of PUC Order Granting Approvals for the MinnCan Pipeline Project | document details PLEASE TAKE NOTICE that on April 13, 2007 the Minnesota Public Utilities Commission issued two separate Orders granting a Certificate of Need and a Pipeline Routing Permit for the MinnCan Pipeline Project
November 17, 2006 Administrative Law Judge Heydinger’s Report providing Findings of Fact, Conclusions and Recommendations in the matter of the MinnCan Pipeline Project | document details The Administrative Law Judge’s Findings of Fact, Conclusions and Recommendation in the Matter of the Application of Minnesota Pipeline Company for a Certificate of Need for a Crude Oil Pipeline and in the Matter of the Application of Minnesota Pipeline Company for a Routing Permit for a Crude Oil Pipeline
February 17, 2006 Pipeline Routing Permit Application-MinnCan Project PUC Docket # PL-PL-05-2003 | document details Minnesota Pipe Line Company MinnCan Project
February 17, 2006 Environmental Assessment Supplement to the Pipeline Routing Permit Application | document details MinnCan Project--Minnesota Pipe Line Company
February 17, 2006 PIPELINE ROUTING PERMIT APPLICATION-FIGURES-- MINNCAN PROJECT PUC DOCKET # PL5/PPL-05-2003 | document details MinnCan Project--Minnesota Pipe Line Company
File register
DateProject nameDescription
April 13, 2007 PUC Order Granting a Route Permit for the MinnCan Pipeline Project | document details Minnesota Public Utilities Commission Order Granting Route Permit for the MinnCan Pipeline Project
April 13, 2007 Notice of PUC Order Granting Approvals for the MinnCan Pipeline Project | document details PLEASE TAKE NOTICE that on April 13, 2007 the Minnesota Public Utilities Commission issued two separate Orders granting a Certificate of Need and a Pipeline Routing Permit for the MinnCan Pipeline Project
February 09, 2007 Supplement to MinnCan Comments and Recommendations | document details Supplement to Comments and Recommendations of the Department of Commerce Energy Facility Permitting Staff in the Matter of the MinnCan Crude Oil Pipeline Project
February 02, 2007 MinnCan Pipeline Route Maps as of January 5, 2007 Pipeline Route Maps in the Matter of the MinnCan Crude Oil Pipeline Indicating the Proposed Route as of January 5, 2007
February 02, 2007 Comments and Recommendations to the Minnesota Public Utilities Commission in the Matter of the MinnCan Project Comments & Recommendations of the Department of Commerce Energy Facility Permitting Staff in the Matter of the MinnCan Crude Oil Pipeline Project
November 17, 2006 Administrative Law Judge Heydinger’s Report providing Findings of Fact, Conclusions and Recommendations in the matter of the MinnCan Pipeline Project | document details The Administrative Law Judge’s Findings of Fact, Conclusions and Recommendation in the Matter of the Application of Minnesota Pipeline Company for a Certificate of Need for a Crude Oil Pipeline and in the Matter of the Application of Minnesota Pipeline Company for a Routing Permit for a Crude Oil Pipeline
August 02, 2006 Notice of Public Meeting and Public Hearings on the MinnCan Pipeline Project | document details Notice of Public Meetings and Public Hearings regarding the applications by Minnesota Pipeline Company for a Certificate of Need and a Pipeline Routing Permit for the 295 mile MinnCan crude oil pipeline project
June 22, 2006 Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipline project | document details Comments and Recommendations of the Commerce Department Staff concerning what additional pipeline alignments, route segments and route alternatives should be accepted by the PUC for consideration at a contested hearing. Attachments to the Comments and Recommendations are listed separately
June 22, 2006 Attachment D of the Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipeline project | document details Attachment D -- Relevant correspondence concerning additional pipeline alignments, route segments and route alternatives.
June 22, 2006 Attachment C of Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipline project | document details Attachment C -- Route/Route Segment Proposals Outside of Proposed Route
June 22, 2006 Attachment B to Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipline project | document details Attachment B -- Alignment Modifications within the MPL Proposed Route
June 22, 2006 Attachment A to Department of Commerce Staff Comments and Recommendations on the selection of route alternatives for the MinnCan Pipline project | document details Attachment A -- Pipeline routing process schematic and other background materials
March 22, 2006 Guidance for Route Proposals | document details This gudiance document provides a summary of what interested parties must do to submit an alternative route or route segment for consideration by the Public Utilities Commission
March 03, 2006 MinnCan Permit Process Schematic | document details Permit process flowchart with dates specific to the MinnCan Project
February 21, 2006 Notice of Pipeline Routing Permit Application Acceptance and Public Information Meetings on the MinnCan Pipeline Project | document details Information Meetings on the MinnCan Pipeline Project
February 17, 2006 Pipeline Routing Permit Application-MinnCan Project PUC Docket # PL-PL-05-2003 | document details Minnesota Pipe Line Company MinnCan Project
February 17, 2006 PIPELINE ROUTING PERMIT APPLICATION-FIGURES-- MINNCAN PROJECT PUC DOCKET # PL5/PPL-05-2003 | document details MinnCan Project--Minnesota Pipe Line Company
February 17, 2006 Environmental Assessment Supplement to the Pipeline Routing Permit Application | document details MinnCan Project--Minnesota Pipe Line Company
January 26, 2006 Briefing Paper re Pipeline Routing Permit Application for the MinnCan Project | document details Staff Briefing Paper Regarding Acceptance of Pipeline Routing Permit Application
January 26, 2006 MinnCan General Project Location Map | document details MinnCan General Project Location Map